When natural gas (NG) is released into the atmosphere, its impact over 20 years as a greenhouse agent is 80 times greater than CO₂.
The oil and gas industry needs cost-effective solutions to monitor methane emissions reductions across all elements of the value chain.
Qnergy provides remote power solutions to help companies improve operational efficiency and reduce emissions.
SeekOps develops and fields advanced sensor technology for the energy sector to detect, localize, and quantify natural gas emissions through integrated drone-based systems.
GHGSat provides accurate, low-cost greenhouse gas monitoring data and services covering any facility in the world.
Using aircraft mounted high-resolution infrared imaging, Kairos is conducting quarterly campaigns of bp’s assets searching for methane leaks.
Eni has adopted a detailed business strategy to reduce net absolute lifecycle emissions, associated with operation and products, by 80% by 2050.
The company is pursuing a broad set of initiatives to achieve this goal, focusing on efficiency gains, methane emissions reduction, portfolio shifts towards lower and zero carbon energy sources, and carbon capture and storage.
CNPC monitors methane emissions from major sources in its full value chain of oil and gas production. Routine flaring is now avoided in both new sites and major existing major ones.
LDAR programmes are designed to systematically identify and repair leaking equipment and components, such as valves, flanges, connectors, pumps, compressors and tanks.
Enagás is a midstream company. It is a leading natural gas infrastructure company in Spain and the Technical Manager of the Spanish gas system.
Wintershall Noordzee (JV Wintershall Dea Gazprom) Offshore The Netherlands, Block K13 pigging station Reduction of Pigging frequency and use of vent gas for power generation.
Terega, a company that operates a transmission system, regularly performs work which requires gas to be vented from pipelines. If gas
Hot tapping is an alternative procedure that makes a new pipeline connection while the pipeline remains in service.
Once the tightness test on a new section of network has successfully finished, but before commissioning, the inner air is purged using a vacuum pump, which extracts the air from the new section.
Implementing analysis and feedback after third-party damage; improving the accuracy of maps of the network; creating partnerships with relevant stakeholders; raise public awareness of the risk of third-party damage.
ExxonMobil is progressing a comprehensive methane management pro-gramme which is on track to meet its goal of reducing methane emissions by 15% in 2020, compared to 2016.
ExxonMobil is progressing a comprehensive methane management pro-gramme which is on track to meet its goal of reducing methane emissions by 15% in 2020, compared to 2016.